What an EPC Company Is, and What Its Risk Transfer Is Actually Worth

EPCM Services

February 19, 2025

25 minutes read

What is an EPC Company

Every EPC contractor's website tells you the same thing: single point of responsibility, risk transfers from you to them. That is true, and it is incomplete in a way that costs owners money.

Risk transfer under an EPC contract is bounded. Overall liability is commonly capped at around 100 percent of the contract price. Delay and performance liquidated damages typically carry sub-caps near 20 percent each. Consequential losses, including the revenue you lose while the plant is not running, are usually excluded entirely.

And all of that is only collectible if the contractor is still solvent, or if you took security that survives them.

This guide covers what an EPC company is, which contract form governs it, where the transfer actually stops, and the checks that tell you whether the contractor can carry what they have agreed to carry.

What an EPC Company Is

An EPC company is a contractor that takes contractual responsibility for engineering, procurement and construction of a facility under a single agreement, and hands over a plant ready to operate.

EPC stands for Engineering, Procurement and Construction. The model's defining feature is single point of responsibility, meaning one party is accountable for design decisions, equipment sourcing and construction quality at the same time, so a design error that causes a construction problem cannot be argued between two firms.

That is the real difference from a general contractor. A general contractor builds to a design someone else completed. An EPC company owns the design as well, which changes the risk profile of the whole project.

The other defining feature is commercial. EPC contracts are typically lump sum and fixed time, with broad transfer of design, coordination and interface risk to the contractor, performance guarantees proven by completion and commissioning tests, and liquidated damages for failure to meet either.

One important thing about the term itself

"EPC" is not a technical term. As LexisNexis puts it in its guidance on EPC contracts, the label EPC or turnkey is descriptive rather than defined in legislation or case law.

That matters more than it sounds. It means no legal definition sets what risk an EPC contract transfers. The transfer is whatever the clauses say, and two contracts both called EPC can allocate risk very differently. Read the contract, not the label.

EPC, LSTK, EPCC and EPIC: The Labels

Several abbreviations describe broadly the same arrangement, and the differences between them are scope boundaries rather than risk allocation.

Label

Stands for

Scope difference

EPC

Engineering, Procurement and Construction

The base model, usually including commissioning in practice

LSTK

Lump Sum Turn Key

Emphasises the commercial structure: one fixed price, plant handed over ready to run

EPCC

Engineering, Procurement, Construction and Commissioning

Makes commissioning explicit in the scope title

EPIC

Engineering, Procurement, Installation and Commissioning

Common offshore and in process plant, where installation rather than construction is the operative activity

Turnkey means the contractor engineers, procures, constructs, tests and commissions, then hands over a facility that can be operated immediately, literally by turning the key.

Do not select a contractor on the label. Confirm in the scope of work whether commissioning, performance testing, initial spares, training and as-built documentation are included, because those five items are where "turnkey" most often turns out not to be.

EPC, General Contractor, or EPCM

Three delivery models, and the choice determines who carries design risk, who manages the interfaces, and how much of your own organisation you need during execution.

Model

Who owns design

Who carries interface risk

Owner resource required

Price structure

EPC / LSTK

Contractor

Contractor

Lowest

Lump sum with a risk premium

Design-Build

Contractor

Contractor, usually narrower scope

Low to moderate

Lump sum or GMP

General contractor (design-bid-build)

Owner or owner's designer

Owner

High

Construction price only

EPCM

Owner, executed by the EPCM firm

Owner

Highest

Reimbursable management fee

Under design-bid-build, the owner commissions a design, then tenders construction against it. Any gap between what the designer drew and what the builder can build is the owner's problem, which is the coordination burden EPC exists to remove.

Under EPCM, the management firm acts as the owner's agent rather than as the contractor. The owner holds the equipment and construction contracts directly, keeps control, and keeps the risk. For a full comparison of when each model is appropriate and what the EPC risk premium costs, see our EPC vs EPCM analysis.

What EPC costs you in owner resource

Less than the alternatives, and not nothing. You still need an owner's team to approve design, witness tests, administer the contract, manage change and take over the plant. Owners who staff an EPC project as though the contractor has removed the need for technical oversight tend to discover the gap at performance testing.

The Three Phases, and Where FEED Actually Sits

An EPC contract covers engineering, procurement and construction, and it almost always begins after front-end engineering design is complete, which means the owner has already fixed the decisions that determine the contractor's risk.

Front-end engineering design, before the EPC contract

Front-end engineering design, or FEED, is the basic engineering study that defines the facility's configuration, major equipment, layout, and performance basis before detailed design begins. It follows the feasibility study and precedes the EPC execution phase.

FEED quality is the single largest determinant of EPC outcome. A contractor bidding lump sum against a weak FEED prices the uncertainty, and every ambiguity becomes a change order later. Owners who underinvest in FEED pay for it twice.

Engineering

The contractor develops detailed design across civil, structural, mechanical, electrical, and instrumentation and control disciplines, working from the FEED basis.

Design freeze is the point beyond which changes require formal variation. Establish it in the contract with a date, because design changes after freeze are the most common route to cost growth on an otherwise fixed-price project.

Procurement

The contractor sources equipment, materials and subcontracted services against the design. On current lead times this phase, not construction, is usually the schedule driver.

Equipment lead times have become the binding constraint on industrial project delivery, and an EPC contractor's schedule is only as credible as their slot positions. For the underlying process, including expediting, inspection documents and Incoterms, see our guide to the industrial procurement process. For sector-specific compliance requirements in oil and gas, see our guide to oil and gas procurement.

Construction and commissioning

The contractor builds, installs, tests and commissions. Where the plant must be in service before construction completes, temporary capacity bridges the gap. See our guide to temporary and mobile power.

Scope change after award

Every change after award is a variation with cost and schedule consequences, and a lump-sum contractor has both the right and the commercial motive to price them firmly. Establish the variation pricing basis, including engineering rates and a schedule impact mechanism, in the contract itself rather than negotiating it under pressure later.

The Contract Form: FIDIC Silver Book and the Alternatives

The FIDIC Silver Book, formally the Conditions of Contract for EPC/Turnkey Projects, is the most widely used standard form for EPC arrangements internationally.

FIDIC published the Second Edition in 2017, updating the 1999 First Edition. It sits within FIDIC's Rainbow Suite alongside the Red Book, Conditions of Contract for Construction, and the Yellow Book, Conditions of Contract for Plant and Design-Build. The Second Editions of all three were published in December 2017, eighteen years after the first editions.

Form

Full designation

Use case

FIDIC Silver Book

Conditions of Contract for EPC/Turnkey Projects, Second Edition 2017

Lump-sum turnkey where the contractor takes design and most risk

FIDIC Yellow Book

Conditions of Contract for Plant and Design-Build, Second Edition 2017

Contractor designs to owner's requirements, with an Engineer administering

FIDIC Red Book

Conditions of Contract for Construction, Second Edition 2017

Owner-designed works, contractor builds

IChemE Red Book

Form of Contract, Lump Sum Contracts

Process plant, lump sum

IChemE Green Book

Form of Contract, Reimbursable Contracts

Process plant, reimbursable

MF/1

Model Form of General Conditions of Contract

Electrical and mechanical plant, published by IMechE and IET

Why the form matters to you

The standard form sets the default position on risk. The Particular Conditions then amend it, and that is where the actual allocation is decided.

FIDIC's General Conditions are protected by copyright and may not be altered without a licence to amend. Amendments belong in the Particular Conditions, Part B. So when you receive a contract described as "FIDIC Silver Book," ask for the Particular Conditions, because that is the document that says what was changed.

Unforeseeable physical conditions

The Silver Book allocates substantially more site and subsurface risk to the contractor than the Yellow or Red Books do, which is part of why it carries a premium. If your site has genuine geotechnical uncertainty, expect either a high price or a carve-out in the Particular Conditions.

What the Risk Transfer Is Actually Capped At

EPC risk transfer is bounded by three limits: an overall liability cap, sub-caps on liquidated damages, and the exclusion of consequential loss. Together they define the real value of the transfer.

Market practice is well established. Most EPC contractors will not accept unlimited liability, and the market position is generally a cap at 100 percent of the contract price. Sub-caps of around 20 percent of contract price on delay liquidated damages and on performance liquidated damages are also common. Consequential damages are generally excluded, and loss of profit is frequently excluded expressly.

What that means in practice

Take a $200 million plant, two years late, that never achieves guaranteed output.

Your delay liquidated damages recovery is capped at roughly $40 million. Your performance liquidated damages recovery is capped at roughly $40 million. Your overall recovery across all heads is capped at roughly $200 million. And the revenue you lost across those two years, which may exceed all of it, is excluded as consequential loss.

That is a substantial transfer. It is not "full project risk off your plate," and any page that tells you otherwise is selling.

The carve-outs

Caps are not absolute. Under the FIDIC Silver Book Second Edition, the cap on delay liquidated damages does not apply in cases of fraud, gross negligence, deliberate default or reckless misconduct, mirroring the carve-outs from the overall liability cap. Breach of patent rights and wilful misconduct are commonly carved out too.

Those exclusions are the exception, not the route to recovery. Establishing gross negligence is a litigation exercise, not a contractual entitlement.

What a wrap guarantee means

A wrap guarantee is the contractor's undertaking to stand behind the performance of the whole plant, including equipment they bought from third parties, rather than passing through the OEM's warranty terms. It is one of the genuine values of the EPC model, and it should be stated explicitly rather than assumed from the word turnkey.

Are contractors still taking lump-sum risk

Less readily than a decade ago, and the terms reflect it. Contractors across power and process have absorbed heavy losses on fixed-price work, and the market has responded with tighter caps, more carve-outs, more allowances and more reimbursable or hybrid structures. Expect to negotiate, and treat a contractor who accepts unusually generous terms without discussion as a solvency question rather than a bargain.

Performance Security: What Makes the Cap Collectible

A liability cap is a number in a contract. Performance security is money you can call. The difference matters enormously if the contractor fails.

The FIDIC Silver Book provides example forms of security that largely adopt the Uniform Rules of the International Chamber of Commerce, including a parent company guarantee, tender security and performance security by way of a demand guarantee or surety bond. Performance security is addressed at Sub-Clause 4.2. The forms provide a framework, and which securities are provided and on what terms is negotiated between the parties.

Instrument

What it is

Strength for the owner

Demand guarantee

A bank undertaking payable on presentation of a compliant demand, independent of the underlying dispute

Strongest. Money arrives without proving breach first

Surety bond

A surety's undertaking, generally conditional on establishing default

Weaker. Recovery depends on proving the case

Parent company guarantee

The contractor's parent undertakes performance or payment

Only as strong as the parent's balance sheet, and worth nothing if the parent is a holding shell

Tender security

Security provided with the bid against withdrawal or refusal to sign

Protects the tender process, not the works

Retention

A percentage of each payment withheld by the owner

Simple and effective, and it accumulates slowly

Demand guarantees are commonly issued subject to the ICC Uniform Rules for Demand Guarantees, URDG 758, which govern how the demand must be presented and when the guarantor must pay.

The question to ask about a parent company guarantee

Which entity is it from, and what does that entity own? A guarantee from a holding company with no operating assets is a document, not security. Ask for the guarantor's audited accounts, not just its name.

Financing and insurance

Project lenders underwrite the EPC package as closely as they underwrite the asset. A bankable EPC contract generally means an acceptable contractor, an acceptable cap structure, and security instruments the lender's counsel recognises. Weak security is one of the most common reasons an otherwise sound project fails to reach financial close.

Insurers price on the same package plus the contractor's loss record. Involve your broker at tender rather than at award, because the insurance position can change which bid is actually cheapest.

Delay and Performance Liquidated Damages

Liquidated damages are pre-agreed sums payable by the contractor for defined failures, and EPC contracts carry two distinct types that protect against two different outcomes.

Delay liquidated damages are payable per day or per week of delay beyond the contractual completion date. They compensate for late delivery.

Performance liquidated damages are payable for failure to achieve the guaranteed performance of the plant, as set out in the Schedule of Performance Guarantees. They compensate for a plant that is finished but underperforms.

The FIDIC Silver Book Second Edition introduced performance liquidated damages into the FIDIC suite for the first time, at Sub-Clauses 9.4, 11.4 and 12.4(b). In sectors where performance parameters must be measured and specific levels achieved before taking over, notably power and process plants, participants commonly used their own more detailed provisions before that.

The Schedule of Performance Guarantees

This is the document that defines what the plant must achieve: output, heat rate or efficiency, emissions, availability, and any process-specific parameter. It also defines the test conditions and the correction methodology.

It is the most consequential technical annexe in the contract, and it is frequently drafted last and reviewed least. Have it reviewed by whoever will operate the plant, not only by whoever is buying it.

If the plant never performs

Below a defined minimum performance level, most contracts give the owner the right to reject rather than to accept with damages. Above it, the owner accepts and takes the liquidated damages. Establish where that line sits before you sign, because "underperforming but accepted" can become a twenty-year operating cost.

If the owner causes the delay

Owner interference, late approvals, late site access or owner-directed changes generally entitle the contractor to an extension of time, and sometimes to cost. Delay is rarely one-sided in practice, and contemporaneous records are what settle it. Require a contractual progress reporting regime and keep your own records.

Taking Over, Defects and Payment

Taking over is the contractual moment when risk in the plant passes from the contractor to you, and it is the single most consequential date in an EPC contract.

The taking-over certificate is issued once the works have passed the specified completion and performance tests. From that point you generally hold the operating risk, the insurance position changes, and the defects notification period begins.

The defects notification period, commonly twelve to twenty-four months, is the window during which the contractor must remedy defects that appear in service. Retention is typically released in stages, part at taking over and the balance at the end of that period.

Prove performance before you sign

Name the test code in the contract. ASME PTC 46, Performance Test Code on Overall Plant Performance, covers whole-plant net output and heat rate. ASME PTC 22, Performance Test Code on Gas Turbines, covers gas turbine output and heat rate. Agree the correction curves, the instrumentation accuracy class and the acceptable measurement uncertainty before the test, not during it.

A performance guarantee whose test method is agreed after the plant is built is a negotiation rather than a guarantee.

How payment is structured

Payment is usually monthly against a schedule of values, a detailed breakdown of the contract price allocated across work phases, with certification by the owner or the Engineer. Milestone payments tied to defined manufacturing and construction events are common for major equipment.

Warranty, O&M and who runs the plant afterwards

Establish whether the equipment warranty runs from delivery or from taking over, because on a long project the difference can be a year or more of coverage. Establish separately who operates and maintains the plant after handover, since the EPC contractor's obligations end with the defects period unless you have contracted otherwise.

How to Verify an EPC Contractor Can Carry the Risk

The contractor's promise to absorb risk is worth exactly what their balance sheet, their security and their track record make it worth, and all three are verifiable before award.

Check

What to require

Evidence to request

Reject if

Contracting entity

The legal entity that will sign, named, with its jurisdiction

Corporate structure and registration

The signing entity is a thinly capitalised special purpose vehicle with no guarantee behind it

Financial capacity

Ability to absorb a loss at the cap without failing

Three years of audited accounts, not group summaries

The cap exceeds the entity's net assets by a wide margin

Bonding capacity

Available surety capacity for this contract value alongside existing commitments

Letter from the surety confirming available capacity

Capacity is fully committed elsewhere

Parent company guarantee

Guarantee from an entity with real assets

Guarantor's audited accounts

The guarantor is a holding shell

Design capability

In-house engineering in the relevant disciplines, not subcontracted wholesale

Organisation chart, discipline headcount, prior design references

Design is fully subcontracted with no accountability chain

Quality and safety systems

ISO 9001:2015 and ISO 45001:2018 with the relevant scope, plus three-year TRIR and EMR

Certificates with scope statements, source safety data

Scope excludes engineering or construction

Delivery record

On-time and on-budget performance on comparable projects

Named reference projects with owner contacts

References decline to speak, or are all in-progress

Subcontractor exposure

Critical subcontractors named and subject to approval

Subcontracting plan

Undisclosed subcontracting of critical scope

Step-in rights

Your right to take over the works on contractor default

Contract clause

Absent

Reference checks that produce real information

Do not ask whether the owner was satisfied. Ask what the contractual completion date was and what the actual one was. Ask how many variations were raised and what they added to the price. Ask whether performance guarantees were met at first test. Ask what the security package was and whether any part of it was called. Ask to speak to the project director, not the commercial contact.

If the contractor becomes insolvent

This is the scenario the security package exists for. Your position depends on whether you hold a demand guarantee callable without proving breach, whether you have step-in rights allowing you to take over the works and subcontracts, whether title to work in progress and materials has passed to you, and whether design documents are licensed to you for completion by another party.

Establish all four at contract. None of them can be obtained afterwards.

Whether to appoint an owner's engineer

An owner's engineer is an independent technical adviser acting for the owner, reviewing design, witnessing tests, administering technical aspects of the contract and verifying that what is delivered matches what was specified.

On a lump-sum EPC project the contractor controls the design, the procurement and the testing. Without independent review, the owner's only check on all three is the contractor's own reporting. The cost of an owner's engineer is typically a small fraction of contract value and it is the single most effective control available to an owner under this model.

How the EPC Decision Changes by Sector

The contract mechanics are constant. What changes is which clause carries the most weight.

Power generation

Performance guarantees dominate, because output, heat rate and availability determine project economics for decades. The Schedule of Performance Guarantees and the ASME test basis are the clauses to get right. Equipment lead times, particularly for turbines and transformers, are now the primary schedule risk. For technology selection before contracting, see our guide to power generation systems compared.

Oil, gas and petrochemicals

The model originated here and is still used most heavily in the sector. Hazardous area compliance, material specification and sector quality systems sit inside the contractor's scope, and the owner must verify they were specified rather than assumed.

Data centers

Schedule certainty outranks price, because a missed go-live date is contractual with the end customer. Interconnection and long-lead electrical equipment are usually the critical path rather than construction.

Renewables

High volume, standardised scopes and thin margins, which means contractor financial strength deserves more scrutiny rather than less. Performance guarantees are typically expressed as an availability or energy yield commitment.

Smaller projects

Below a certain contract value the EPC risk premium and the transaction cost of a full FIDIC-based package are hard to justify. Design-build or a managed multi-contract approach is frequently better value.

Outside the United States

FIDIC forms are the international default and are widely used across Europe, the Middle East, Africa and Asia. In the US market, EPC arrangements are more often written on bespoke or industry forms rather than FIDIC. Local content requirements, permitting regimes and governing law and dispute resolution provisions all vary, and they belong in the evaluation rather than in the small print.

What Prismecs Does

Prismecs delivers engineering, procurement and construction management, installation and commissioning, and operations and maintenance, and provides independent owner's engineering on projects where the requirement is verification rather than delivery.

Those are two different roles and Prismecs takes one or the other on any given project, never both. An adviser who also bids the resulting work cannot give the advice the role exists to provide, which is why our owner's engineering service is offered on that basis. Our delivery capability sits under EPCM services.

Delivered project scope includes eight TM2500 dual-fuel units totalling 260 MW at Birr, Switzerland, delivered as a fast-track reserve plant online in six months on a compact site with a new 220 kV interconnection; four TM2500 units totalling 110 MW at Duqm, Oman with O&M crews, CMMS and parts support; an LM2500XPRESS plant at Miaoli, Taiwan delivered in ten months; three LM6000PC units installed and commissioned adding 150 MW of fast-start reserve; and an LM6000 fleet decommissioned in Norway, transported, then reassembled and recommissioned at a new site.

Apply this article's checks to any contractor, including us. Ask which legal entity signs. Ask for the security package and who issues it. Ask for the ASME test code that will prove performance. Ask for the project director on a comparable job.

To request an independent review of an EPC bid package or contract, send the draft contract, the scope of work and the Schedule of Performance Guarantees to sales@prismecs.com or call +1 (888) 774-7632. We return a risk allocation summary, a security package assessment and a list of the clauses we would negotiate.

Frequently Asked Questions

What does EPC company mean?

An EPC company is a contractor that takes responsibility for Engineering, Procurement and Construction under a single agreement, delivering a facility ready to operate. Its defining feature is single point of responsibility, meaning one party is accountable for design, sourcing and construction simultaneously. The model is used in power generation, oil and gas and critical infrastructure where cost control, schedule certainty and technical accountability cannot be split across multiple parties.

Is EPC a contractor?

Yes. An EPC contractor assumes contractual ownership of all three phases under a unified agreement with the owner. The distinction from a general contractor is design ownership: a general contractor builds to a design someone else completed, while an EPC company owns the design as well. That single difference changes the risk profile of the entire project, because a design error causing a construction problem has only one owner.

Does an EPC contract transfer all project risk to the contractor?

No. Risk transfer is bounded. Market practice caps overall liability at around 100 percent of the contract price, with sub-caps near 20 percent each on delay and performance liquidated damages. Consequential damages and loss of profit are generally excluded, which means the revenue you lose while a plant is late or underperforming usually falls outside the recovery. The transfer is substantial and it is not total.

What is the FIDIC Silver Book?

The FIDIC Silver Book is the Conditions of Contract for EPC/Turnkey Projects, published by the Fédération Internationale des Ingénieurs-Conseils. The Second Edition was published in 2017, updating the 1999 First Edition, and it sits alongside the Red Book for construction and the Yellow Book for plant and design-build. It allocates substantially more design, interface and site risk to the contractor than the other two forms.

What is the difference between delay and performance liquidated damages?

Delay liquidated damages are payable per day or week of delay beyond the contractual completion date, compensating for late delivery. Performance liquidated damages are payable for failure to achieve the guaranteed performance set out in the Schedule of Performance Guarantees, compensating for a plant that is finished but underperforms. The FIDIC Silver Book Second Edition introduced performance liquidated damages to the FIDIC suite for the first time.

What is a typical EPC liability cap?

Most EPC contractors will not accept unlimited liability, and the general market position is a cap at 100 percent of the contract price. Sub-caps of around 20 percent of contract price on delay liquidated damages and on performance liquidated damages are common, and consequential damages and profit are usually excluded. Caps are typically carved out for fraud, gross negligence, deliberate default and wilful misconduct.

What performance security should I require from an EPC contractor?

The FIDIC Silver Book provides example forms adopting ICC Uniform Rules, including a demand guarantee, a surety bond, a parent company guarantee and tender security, with performance security addressed at Sub-Clause 4.2. A demand guarantee is strongest for the owner because it is payable on a compliant demand without first proving breach. A parent company guarantee is only as strong as the guarantor's balance sheet.

What happens if my EPC contractor becomes insolvent?

Your position depends entirely on what you secured at contract. Four things determine recovery: whether you hold a demand guarantee callable without proving breach, whether you have step-in rights allowing you to take over the works and subcontracts, whether title to work in progress and materials has passed to you, and whether design documents are licensed to you for completion by another party. None can be obtained after the event.

What is FEED and when does it happen?

Front-end engineering design is the basic engineering study defining a facility's configuration, major equipment, layout and performance basis. It follows the feasibility study and precedes the EPC execution phase, which means it is usually complete before the EPC contract is awarded. FEED quality is the largest single determinant of EPC outcome, because a contractor bidding lump sum against a weak FEED prices the uncertainty and recovers the rest through variations.

What is taking over and why does it matter?

Taking over is the contractual moment when risk in the plant passes from contractor to owner, evidenced by a taking-over certificate issued once the works have passed specified completion and performance tests. From that point the owner generally holds operating risk, the insurance position changes, and the defects notification period begins, commonly running twelve to twenty-four months with retention released in stages.

Which test code proves EPC performance guarantees?

ASME PTC 46, Performance Test Code on Overall Plant Performance, covers whole-plant net output and heat rate. ASME PTC 22, Performance Test Code on Gas Turbines, covers gas turbine output and heat rate. Name the code in the contract and agree the correction curves, instrumentation accuracy class and acceptable measurement uncertainty before the test. A method agreed after the plant is built is a negotiation, not a guarantee.

Which contract type is riskiest for the contractor?

The fixed-price lump sum EPC contract, because it locks in project cost regardless of actual expenditure, so scope creep, material price escalation or construction delay erodes the contractor's margin directly. In volatile markets like oil and gas or large-scale power infrastructure, this structure demands exceptional procurement foresight and engineering precision to remain viable, which is why it carries a risk premium in the price.

What is LSTK, EPCC and EPIC?

LSTK means lump sum turn key and emphasises the commercial structure: one fixed price, plant handed over ready to run. EPCC adds commissioning explicitly to the scope title. EPIC means engineering, procurement, installation and commissioning, common offshore and in process plant where installation rather than construction is the operative activity. They describe broadly the same arrangement with different scope boundaries, so confirm the scope of work rather than relying on the label.

Should I appoint an owner's engineer on an EPC project?

On a lump-sum EPC project the contractor controls design, procurement and testing, so without independent review your only check on all three is the contractor's own reporting. An owner's engineer reviews design, witnesses tests, administers technical aspects of the contract and verifies that what is delivered matches what was specified. The cost is typically a small fraction of contract value and it is the most effective control available under this model.

Tags: EPC Contractor FIDIC Silver Book EPC Liability Cap Performance Security Owner's Engineering