The most valuable thing digitalization delivers on an EPC project is not construction efficiency. It is the data you own when the contractor leaves.
That outcome is decided before award, in a document most owners do not write. The Exchange Information Requirements specify what model, in what format, at what level of detail, is delivered at handover. Without it, an owner receives whatever the contractor happened to produce.
The framework governing this is ISO 19650, the international standard for information management using building information modelling. Its 2026 revision makes the point explicit: the distinction between delivery phase and operational phase has been removed, and the handover data drop disappears in favor of information that flows continuously.
For an industrial operator, that changes the question from how the project is built to what the asset register looks like on day one of operation.
This guide covers what digitalization actually does at each EPC phase, the standards that govern it, and what to specify so the model becomes an operating asset rather than a folder of files.
Digitalization in EPC rests on one framework and three phase-specific applications, and the framework is what makes the applications work together.
Building information modelling, under ISO 19650-1:2018 clause 3.3.14, is the use of a shared digital representation of a built asset to facilitate design, construction and operation processes, to form a reliable basis for decisions.
The phrase that matters is “reliable basis for decisions.” A model nobody verifies is not that, and an unverified as-built model is worse than none because it is trusted.
What follows covers the three major phases, and the standards and deliverables attached to each.
Clash detection identifies physical conflicts between disciplines before construction, which is where the model repays its cost fastest. Federating the structural, mechanical, electrical and piping models exposes conflicts that two-dimensional coordination misses.
Procurement benefits from digitalization through quantity extraction and supplier integration, and both depend on data quality rather than on software.
Quantity take-off pulls material quantities directly from the model, replacing manual measurement from drawings. Its accuracy is governed by the model’s level of detail, which means quantities taken from a concept-stage model are indicative rather than contractual.
Artificial intelligence helps predict material demands based on project progression and historical usage, part of a wider shift toward technology-driven, predictive procurement across EPC supply chains.
Smart procurement platforms integrate with suppliers and can trigger orders against defined thresholds, and digital procurement systems allow real-time monitoring of commitment against budget.
Digitalization delivers value in five areas, and the largest one arrives after the project is finished.
It does not come from the software, and it does not come from having a model. It comes from using the model to make decisions earlier, which requires the decisions to be scheduled around the model’s maturity rather than around the drawing issue dates.
Digitalization compresses schedule mainly by removing waiting time between disciplines, not by making individual tasks faster.
In a document-based workflow, a discipline waits for another discipline’s drawing issue. In a CDE-based workflow, work-in-progress information is visible as it develops, so downstream work starts earlier at a known level of confidence.
Clash detection before construction removes site stoppages that would otherwise interrupt the programme, and model-linked progress measurement surfaces slippage earlier, when recovery is still cheap.
A 2026 industry outlook reports that 72 percent of infrastructure owners now mandate LOD 500 for project handover, to ensure operational data integrity for facility management.
ISO 7817-1 defines Level of Information Need, which replaces the ambiguous LOD term. LOD was interpreted differently across countries and organizations for years, and the new term requires the client to specify the geometry and information required for each specific purpose rather than selecting a numbered level.
Specify by purpose. “LOD 500” means less than “sufficient to populate the maintenance management system with asset tag, manufacturer, model, serial number and maintenance requirement.”
Insurers and lenders assess the completeness of handover documentation when underwriting an operating asset. A verified asset information model is stronger evidence than a drawing set, and an unverified one creates exposure if it is relied upon and proves wrong.
A model does not make an asset efficient. It makes the data available to find out whether it is, which is a prerequisite rather than an outcome.
In operations, not in construction. An owner who receives a verified AIM starts operating with a populated maintenance management system. An owner who receives PDFs spends the first year of operation rebuilding the asset register by walking the plant.
That rebuild is the hidden cost of an unspecified handover, and it is incurred at exactly the point when the operating team has least capacity.
Three obstacles recur in EPC digital adoption, and only one of them is technical.
Information management under ISO 19650 is a defined role, not an addition to an engineering job. The appointing party needs someone who owns the EIR, the CDE configuration and the acceptance of delivered information.
Where that role is unstaffed, the requirements are written once and never enforced.
Integrating digital tools with legacy systems is the technical obstacle, and open formats are the mechanism that makes it tractable.
Industry Foundation Classes, or IFC, is the open, software-neutral format for exchanging model data between different authoring tools. It is what prevents an owner being locked into whichever platform the contractor chose.
COBie, Construction Operation Building Information Exchange, is a structured data format for transferring asset data from the model into a facility or maintenance management system at handover. It is the bridge between the model and the CMMS.
ISO 19650-4 specifies the processes for information exchange, including the technical requirements for file formats and information containers.
Require delivery in IFC alongside any native format, and require COBie or an equivalent structured export mapped to your maintenance management system’s fields.
Specifying only the native format means the data is only usable for as long as you hold that licence.
That is normal and it is what IFC exists for. The requirement is not that everyone uses the same tool; it is that everyone can export to a common format that validates.
Require a test exchange early in the project rather than discovering the export is incomplete at handover.
ISO 19650 applies internationally and is the basis of national frameworks in the UK and elsewhere. In the United States, NBIMS-US and COBie requirements may apply, particularly on federal contracts. Confirm which framework governs before writing the EIR.
Prismecs delivers EPC and owner’s engineering on industrial energy projects, and the digital question we help owners answer is what to require rather than which platform to buy.
Delivered project scope includes eight TM2500 dual-fuel units totaling 260 MW at Birr, Switzerland, online in six months with a new 220 kV interconnection and engineered noise controls on a compact site; four TM2500 units totaling 110 MW at Duqm, Oman, kept grid-ready with resident O&M crews, CMMS and parts support; an LM2500XPRESS plant at Miaoli, Taiwan delivered in ten months; and an LM6000 fleet decommissioned in Norway, transported and recommissioned at a new site.
The Duqm arrangement is the relevant reference for this subject. Resident crews operating against a maintained CMMS with parts support is the operating state a good handover produces, and the state a poor one prevents.
Ask for a redacted BIM Execution Plan from a comparable project. Ask which CDE they use and who administers it. Ask for a sample IFC export and try to open it. Ask what their last project’s handover data looked like and whether the client’s maintenance system was populated from it.
One scope boundary worth stating. Prismecs delivers engineering, procurement, construction management, commissioning and operations. BIM authoring, digital twin software implementation, AI platform deployment and enterprise systems integration are software disciplines with separate providers. Our role is specifying what the owner requires and verifying what is delivered against it.
The 2026 revision of ISO 19650 removes the distinction between delivery phase and operational phase, which changes what an owner must specify and when.
The focus of the standard is now explicitly the whole life of the asset, with the delivery and operational phase distinction removed. Three consequences follow for owners.
Information requirements must cover the entire lifecycle, so the AIR, PIR and EIR are written once against operational need rather than separately for project and operations.
The data drop disappears. Information flows continuously rather than being handed over in a single event at practical completion, which removes the moment where everything either works or does not.
Facility managers are engaged from the concept phase rather than at handover, because they are the people who know what the asset information model needs to contain.
Write the AIR before the next project starts, with the operating team in the room. Everything else in the information chain derives from it.
Digitalization in EPC is governed by ISO 19650, delivered through a common data environment, and judged by what the owner can operate with afterwards.
The Exchange Information Requirements decide that outcome and are written before award. The Asset Information Model is the deliverable that matters, verified as-built, exchanged in IFC, and mapped into the maintenance management system through COBie or an equivalent.
Clash detection, 4D progress measurement and quantity extraction all repay their cost during construction. The larger return arrives when the operating team starts work with a populated asset register rather than a filing cabinet.
Prismecs provides EPC delivery, owner’s engineering, commissioning and operations for industrial energy projects, including specification and verification of handover information requirements.
Capability spans EPC services for project delivery, owner’s engineering for independent technical representation and information requirement review, I&C services for installation, commissioning and controls, O&M services for the operating phase, technology and consulting for assessment and options analysis, and supply chain solutions for procurement and expediting. Delivered work is on the projects page.
Apply this article’s criteria to any proposal, including ours. Ask who writes the Exchange Information Requirements and when. Ask what level of information needed is specified for handover and against what purpose. Ask for a sample IFC export and open it. Ask how the as-built model is verified before acceptance.
To discuss EPC delivery, owner’s engineering or handover information requirements, send your project scope and capacity, contract form if selected, current project stage and your maintenance management system to sales@prismecs.com or call +1 (888) 774-7632.
Under ISO 19650-1:2018 clause 3.3.14, building information modelling is the use of a shared digital representation of a built asset to facilitate design, construction and operation processes, to form a reliable basis for decisions. In EPC it is the engineering deliverable, the clash detection mechanism, the quantity source for procurement, and the basis of the asset register handed over at completion.
The international standard for information management using building information modelling. Part 1 covers concepts and principles including the common data environment. Part 2 covers the delivery phase during design and construction. Part 3 covers the operational phase and the transition from project to asset information model. Part 4 covers information exchange. Part 5 covers security. Part 6 covers health and safety information.
The EIR specifies what information the appointed party must deliver, when, and in what format. The appointing party, meaning the owner, writes it before appointment, derived from the Asset Information Requirements that define what is needed to operate the asset. Without an EIR, the contractor delivers to its own standard, which is optimized for building the asset rather than for operating it.
The agreed single source of information for a project or asset, with defined workflow states controlling what is in progress, shared, published and archived. Information containers move through those states under approval, so a recipient always knows whether what they are viewing is a work in progress or an approved issue. The appointing party establishes or approves it before appointment.
The Project Information Model is produced during design and construction. The Asset Information Model is what the owner operates with afterwards, holding equipment identity, location, specification, maintenance requirement and attached documentation. ISO 19650-3 governs the transition and the operational phase. The AIM is effectively the operating asset register, which is where the commercial value of the whole exercise lands.
LOD 500, as-built and field-verified, is the handover standard, and a 2026 industry outlook reports 72 percent of infrastructure owners now mandating it to ensure operational data integrity. LOD 300 applies at detailed design and coordination, LOD 350 at issue for construction, and LOD 400 at construction with fabrication detail. Specify by operational purpose rather than by number alone.
LOD is Level of Development, covering geometric precision and the reliability of the element. LOI is Level of Information, covering the non-graphical data attached to it. Geometry alone does not satisfy an asset owner, because the operating value is in the data: asset tag, manufacturer, model, serial number and maintenance requirement. Both must be specified separately.
ISO 7817-1 defines Level of Information Need, which replaces the ambiguous LOD term. LOD was interpreted differently across countries and organizations for years, meaning Level of Detail, Level of Definition or Level of Development depending on context. The new approach requires the client to specify the geometry and information required for each specific purpose rather than selecting a numbered level.
IFC, Industry Foundation Classes, is the open software-neutral format for exchanging model data between different authoring tools, preventing lock-in to whichever platform the contractor chose. COBie, Construction Operation Building Information Exchange, is a structured data format for transferring asset data from the model into a facility or maintenance management system at handover. Require both alongside any native format.
The revision removes the distinction between delivery phase and operational phase, focusing the standard explicitly on the whole life of the asset. Information requirements must cover the entire lifecycle rather than stopping at handover. The data drop disappears, with information flowing continuously instead of transferring in a single event. Facility managers are engaged from the concept phase rather than at handover.
Because an owner who receives a verified asset information model starts operating with a populated maintenance management system, while an owner who receives PDFs spends the first year of operation rebuilding the asset register by walking the plant. That rebuild is the hidden cost of an unspecified handover, incurred exactly when the operating team has least capacity.
By field verification against the physical installation, which is the step most frequently omitted. An as-built model that has not been verified records design intent rather than what was installed, and an unverified model is worse than none because it is trusted. Require verification as a condition of handover acceptance and spot-check it before releasing the associated payment.
It predicts schedule slip from progress and historical patterns, identifies design conflicts by comparison with completed projects, optimizes logistics sequencing, and extracts obligations from contract documents. Its accuracy is capped by data quality, and it requires structured project records with consistent coding across multiple completed projects. It narrows where to look rather than replacing engineering or commercial judgement.
Ask for a redacted BIM Execution Plan from a comparable project. Ask which common data environment they use and who administers it. Ask for a sample IFC export and try to open it. Ask what their last project’s handover data looked like and whether the client’s maintenance system was populated from it. Those four questions reveal more than any capability statement.
Tags: BIM ISO 19650 EPC Digitalization Asset Information Model Handover
O&M Services
12 minutes read
Combustion vs Hot Gas Path vs Major Inspection: What Each Covers and When It's Due
Combustion vs hot gas path vs major inspection timing is not just hours. A peaker can owe an HGPI in 4 years on starts alone. Check which limit hits y...
O&M Services
15 minutes read
Writing a Power Plant O&M RFP That Gets Comparable Bids
Write a power plant O&M RFP every bidder must price the same way. Get the pricing template, data room checklist and weighted scorecard that expose eve...
EPCM Services
19 minutes read
25 Questions to Ask a Power Plant EPC Contractor Before You Sign
Most lists of questions to ask an EPC contractor stop at the question. Get why each matters, the strong answer, the red-flag reply and a weighted bid...
Gas Turbines
19 minutes read
Dual-Fuel Gas Turbines: How Gas-and-Liquid Fuel Flexibility Works
A dual-fuel gas turbine switches from natural gas to diesel at load, but most failures start in idle oil lines. Get transfer steps and coking fixes be...